Budget items

budget itemBudget items are the individual line-items of a Budget iconbudget on a Programme iconprogramme, Project iconproject, Subproject iconsub-project or Change requests iconchange request. Budget items can be any costs baseline for the parent asset for example hardware, resources, 3rd party licences etc.A budget item is dependent on two attributes of the parent asset:
Start dateIf the asset start date is set then the month intervals for the budget item will be based on that start date.
Budget intervalsThe number of months allowed in the budget item is set using this asset attribute.
Budget items can contain:
BaselineThis is the original budget for the item. It may be locked through Workflow iconworkflow.
Approved changesOnce the budget item has been baselined any changes must be Pass iconapproved through the steering committee and can then be added to this field.
SavingsThis is the savings related to this initiative.
DeferralsThis is any deferrals related to this initiative.
Total budgetThe total budget adds up the baseline, approved changes, savings and deferrals.
Uncommitted forecastThis is the forecast from the programme/project manager for this budget item. This forecast should not include committed expenditure. If the uncommitted forecast is left blank then Psoda will automatically calculate it as the sum of the baseline and approved changes minus the committed forecast.
Forecast changesYou can capture any changes to your forecast here if you do not want to change the Uncommitted Forecast line.
Committed forecastThis is a forecast of the committed expenditure on the programme/project.
Total forecastThe total forecast adds up the uncommitted forecast, forecast changes and committed forecast.
Budget items also show:
ActualThis is the actual expenditure against this budget item. It is calculated by adding all the expenses logged for this budget item.
VarianceThe variance is calculated to show the difference between the planned and the actual expenditure. The variance calculation is explained in more detail below.
When costs are captured against the project they can be allocated to an applicable budget item. That way you can track the actual expenditures against the original baselines.Budget items can be grouped into sub-groups of the budget, down to as many levels as is required. The baselines from the items are summed into the sub-group; and ultimately into the budget.A workflow can also be selected for each budget. When you Add iconadd the budget item you can select the Standard Budget Item Workflow, or you can Add iconadd a new workflow for budgets specific to your organisation.

Calculating variance

Variance shows the difference between the planned and the actual expenditure. It is calculated as follows:
  • If uncommitted forecast is set then
    • variance = actual – (uncommitted forecast + committed forecast)
  • If uncommitted forecast is blank then:
    • If committed forecast > baseline + approved changes then
      • variance = actual – committed forecast
    • Else
      • variance = actual – (baseline + approved changes)